Floor Space Analysis Workgroup Update – February 26, 2015

26 Feb

The Department of Transportation and Development completed the relocation their Data Center equipment into the Information Services Building (ISB) on December 13th.

The Department of Corrections has been working with the Office of Technology Services and the Office of Telecommunications Management in planning the relocation their data center equipment from their Mayflower Street location into the Department of Public Safety (DPS) Data Center.

LSU Health Science Center has also begun the process of migrating equipment from their racks into Server PODs within the DPS Data Center. The migration is estimated to be completed by July 1, 2015.

The Office of Telecommunications Management has been successfully relocated to the Galvez building.